Upgrading and improvement of 6/0.4 kV electricity distribution network in Bayan-Undur soum, Orkhon province

Upgrading and improvement of 6/0.4 kV electricity distribution network in Bayan-Undur soum, Orkhon province

Project Name: Upgrading and improvement of 6/0.4 kV electricity distribution network in Bayan-Undur soum, Orkhon province

Client: Energy Project-2

Project brief: The project was implemented under the Energy Project-2 with financing from the World Bank.

Completed tasks: 8971 reinforced concrete poles, 268 km SIP-2A transmission wires, 14,484 smart meters for households in ger districts, 877 smart meters for private entities, 9 new overhead substations, and 60 residential electricity supply upgrading works were completed.